| 02/05/2009 2200 MW EMAL Interconnection Network Studies |
|
|
2200 MW EMAL Interconnection Network Studies started in Paris, France. A large aluminum producer EMAL has decided to install a large factory more...[...]
2200 MW EMAL Interconnection Network Studies started in Paris, France. A large aluminum producer EMAL has decided to install a large factory in Abu Dhabi close to Taweelah substation. The consumption is forecasted at 1200 MW for the two pot lines and with its own generation to feed this demand, two combined cycle blocks (two Gas turbines and one steam for each block) and two additional gas turbines will be installed for a total capacity around 2200 MW). This factory is planned to be in operation for the year 2010. TRANSCO (Abu Dhabi power company) requires to evaluate the impact of this new large customer to its system, for that purpose it has requested EDF assistance. This project will be realized jointly by EDF CIST and EKC under long term cooperation agreement.
|
|
|
| 23/03/2009 Next SECI work group meeting will be held in Istanbul |
|
|
Next SECI work group meeting will be also held in Istanbul in Turkey on 25-26th March more...[...]
Next SECI work group meeting will be also held in Istanbul in Turkey on 25-26th March. In this two day session all ongoing activities will be reviewed (update of regional model for 2015 and 2020, progress on ongoing activities etc.), and also presentation of dynamic model for 2015. One of other major issue will be start of new study “Uncertainties in the SEE Transmission Network and Evaluation of Risk for Future Infrastructure Investments”. Second day, joint session with BSTP project working group will be held in which both project experts will able to demonstrate their achievements and exchange of experience.
|
|
|
| 23/03/2009 Next Black Sea work group meeting will be held in Istanbul |
|
|
Next Black Sea work group meeting will be held in Istanbul in Turkey on 25-26th March. In this two day session all ongoing activities will be reviewed more...[...]
Next Black Sea work group meeting will be held in Istanbulin Turkey on 25-26th March. In this two day session all ongoing activities will be reviewed…(update of regional model for 2010 and dynamic model building 2010, progress on ongoing activities etc.) and also extending the project models to 2015. One of other major issue will be finalization of load flow models for 2010 and finalization of initial dynamic model (corresponds to regional model 2010). Second day, joint sesion with SECI project working group will be held in which both project experts will able to demonstrate their achievements and exchange of experience.
|
|
|
| 26/01/2009 Western Balkans Infrastructure Projects Facility - Energy – Montenegro |
|
|
Western Balkans Infrastructure Projects Facility - Energy – Montenegro startedwith kick-off meeting in Podgorica, Montenegro more...[...]
Western Balkans Infrastructure Projects Facility - Energy – Montenegro started with kick-off meeting in Podgorica, Montenegro. Western Balkans Infrastructure Projects Facility (IPF) is a project that has been established with the aim of increasing the number of projects in the region that can be put forward to financial institutions for funding, and therefore to implementation. The project helps countries develop projects and programs that will further economic development in those countries, and then tries to match those developed projects with financiers. IPF is an EU-funded project, and is being implemented by a consortium of international expertise, led by WYG International. The project is expected to continue operating until 2012. with main objective to support the development and upgrading of infrastructure, to help create the conditions for sustainable economic development in the region.
|
|
|
| 29/10/2008 Next Black Sea work group meeting will be held in Lviv |
|
Next Black Sea work group meeting will be held in Lviv in Ukraine on 3-4th December more...[...]
Next Black Sea work group meeting will be held in Lviv in Ukraine on 3-4th December. In this two day session all ongoing activities will be reviewed (update of regional model for 2010 and dynamic model building 2010, progress on ongoing activities etc.). Major issue will be presentation of initial dynamic model (corresponds to regional model 2010) and its finalization. One of major activities is review of Transmission Planning Criteria used in BSR.
|
|
|
| 20/10/2008 Next SECI work group meeting will be held in Sarajevo |
|
Next SECI wourk group will be held in Sarajevo on 6-7th November. In this two day session more...[...]
Next SECI wourk group will be held in Sarajevo on 6-7th November. In this two day session all ongoing activities will be reviewed (update of regional model for 2015 and 2020, progress on ongoing activities etc.). One of major future activities is start of new regional study, on which discussion has been made. It will deal with uncertainties in transmission network planning and reliability of transmission system.
|
|
|
| 24/07/2008 Cooperation agreement between EDF-CIST and EKC |
|
Cooperation agreement between EDF-CIST and EKC is signed more...[...]
Cooperation agreement between EDF-CIST and EKC is signed in joint meeting held in Belgrade. After successful cooperation on numerous studies, EDF-CIST (Centre d'Ingénierie Système Transport) and EKC decided to extend they present cooperation in numerous fields of electrical engineering. This Long term agreement is basis for future more intensive cooperation between two companies.
|
|
|
| 10/07/2008 SECI work group meeting was held in Budapest |
|
|
SECI work group meeting was held in Budapest on 10-11th July. In this two day session more...[...]
SECI work group meeting was held in Budapest on 10-11th July. In this two day session all ongoing activities have been reviewed (update of regional model for 2015 and 2020, progress on ongoing activities etc.). One of major future activities is start of new regional study, on which discussion has been made. It will deal with uncertainties in transmission network planning and reliability of transmission system.
|
|
|
| 21/06/2008 Operational studies for the OMAN Interconnection is finished |
|
Results show that integrated operation of United Arab Emirates and Oman is feasible more...[...]
Results show that integrated operation of United Arab Emirates and Oman is feasible. This study is done in cooperation with EDF-CIST who is leader of this project. Synchronization of two systems is expected in October.
|
|
|
| 05/05/2008 UCTE-IPS/UPS Feasibility Study has been completed |
|
|
After a 3-year investigation phase UCTE-IPS/UPS Feasibility Study, study analysing the feasibility of a possible synchronous coupling of the power systems of IPS/UPS with UCTE has been completed. Based on the study results UCTE has been worked out and endorsed together with its Eastern project partners the key conclusions of the study more...[...]
After a 3-year investigation phase UCTE-IPS/UPS Feasibility Study, study analysing the feasibility of a possible synchronous coupling of the power systems of IPS/UPS with UCTE has been completed. Based on the study results UCTE has been worked out and endorsed together with its Eastern project partners the key conclusions of the study...This Study has investigated the synchronous coupling of the IPS/UPS and UCTE power systems under consideration of key technical, organizational and legal aspects.
Study brings to evidence that a synchronous coupling between UCTE and IPS/UPS is feasible upon implementing several technical, operational and organizational measures and establishing the legal framework as identified in the study.
Regarding the transfer capacities across the interface the steady state analysis shows that the potential power exchanges between UCTE and IPS/UPS are limited mainly due to internal congestions in the systems concerned. Therefore, a synchronous coupling would require investments in the transmission grids on both sides of the interface in order to maintain the transfer capacities available to the markets at present in both synchronous areas. Additional transmission system investments are necessary to ensure significant increase of power exchanges.
Performed dynamic stability analysis underlines the sensitivity to inter-area power oscillations of the synchronously coupled system structure. While ordinary operational disturbances are withstood by both the coupled and uncoupled systems, severe disturbances lead to wide-area oscillations in the coupled systems which could decrease system security. Necessary countermeasures require investments both in the generation and transmission sectors.
Study reveals the need for further investigations to refine and endorse the above mentioned measures and requirements. Major identified areas for further studies are:
a. verification of the IPS/UPS dynamic performance by longer-time observations
b. analysis of emergency situations in IPS/UPS caused by severe disturbances with purpose to adapt and harmonize the currently existing operational guidelines, defence and restoration plans of both synchronous areas.
c. analysis of organizational aspects of the synchronous operation under consideration of several control blocks in IPS/UPS.
In order to achieve a joint, world-largest electricity market platform between UCTE and IPS/UPS synchronous areas the construction of High Voltage Direct Current (HVDC) links between the interface countries may be considered as a medium-term alternative solution for system coupling which, however, deserves separate investigations.
The completion of the Feasibility Study has opened a new era in the cooperation between Western and Eastern TSOs/companies responsible for a reliable operation of the transmission systems and has delivered substantial achievements for both experts and companies’ executives in both systems in terms of working methods, implemented tools and building up mutual understanding.
Source: www.ucte-ipsups.org/news
|
|
|
| 03/05/2008 CARTRANS project in Central Asia |
|
Software training session was held in Ashgabat (Turkmenistan) with EKC experts as lecturers more...[...]
Software training session was held in Ashgabat (Turkmenistan) with EKC experts as lecturers. Project started in August 2007 (conducted by USAID and USEA), and EKC has very active role as project coordinator and consultant.
|
|
|
| 07/04/2008 Black Sea Regional Transmission Planning Project continued |
|
In Varna (Bulgaria) working meeting has been held and also course “Power system analyses - Dynamic modeling” more...[...]
In Varna (Bulgaria) working meeting has been held and also course “Power system analyses - Dynamic modeling” held by EKC experts. Goal of the course was to train BlackSea region experts in dynamic modeling in order to complete regional dynamic model.
|
|
|
... Archive |
|