Procedure for Compliance Testing of Power Park Modules

Montenegro
Procedure for Compliance Testing of Power Park Modules

client: CGES (Montenegro)

type: Consultancy services (Policies,  Generation)

finishing date: March 2016

team: Nebojsa Jovic – Project Manager, M. Vukovic – Consultant, M. Ivanovic

Within the compliance testing procedure, it is necessary to define general and technical requirements for conducting the tests in accordance with national grid code and ENTSO-E Network Code for Requirements for Grid Connection Applicable to all Generators.

General requirements comprise the following topics:

  • Requirements for technical and other documents that Investor must submit to CGES including the detailed testing protocol
  • Requirements that must be fulfilled by the Investor before, during and after conducting of compliance testing
  • Responsibilities of CGES and Investor during compliance testing
  • Time-milestones for compliance testing

Technical requirements comprise specification of all on-site tests that need to be conducted as well as criteria for evaluating the test results. Technical requirements comprise the following sections:

  • Active power control
  • Voltage control
  • Fault-ride through capability
  • Power quality in accordance with EN 61400-21
  • Telecommunication

Type of services provided:

  • Consultancy services