References

Transmission, Software

Serbia

Building of CGMES Node-Breaker Model of Serbian Grid

client: Elektromreza Srbije AD (Serbia)

type: Analysis (Software, Transmission)

finishing date: March 2019

team: Danka Todorovic – Project Leader, Z. Vujasinovic – Consultant, B. Brdjanin, B. Lutovac, I. Aljancic

Generation, Transmission

Bosnia and Herzegovina
Connection Study of small HPP Bočac 2 (10 MVA) to the Distribution Network of Bosnia and Herzegovina

Connection Study of small HPP Bočac 2 (10 MVA) to the Distribution Network of Bosnia and Herzegovina

client: ZP Elektrokrajina a.d. Banja Luka (Bosnia and Herzegovina)

type: Report

finishing date: January 2019

team: Milan Stojanovic - Project Manager, N. Jovic - Consultant, M. Ivanovic 

Software

Austria
TNA: Upgrade of PFC Function for APG

TNA: Upgrade of PFC Function for APG

client: Austrian Power Grid - APG (Austria)

type: Software

finishing date: October 2018

team: Dusan Vlaisavljevic – Project Manager, Z. Vujasinovic and I. Mihajlovic-Vlaisavljevic – Consultants, B. Lekovic

Transmission

Montenegro
Study of Electricity Losses in Transmission Network of Montenegro

Study of Electricity Losses in Transmission Network of Montenegro

client: CGES a.d. (Montenegro)

type: Study

finishing date: October 2018 (February 2019)

team: Milan Ivanovic - Project manager, B. Sijakovic, B. Brdjanin, S. Markovic and M. Vukovic - Consultants

Market, Software

Austria, WB6
Technical Assistance to the Implementation of Cross-border Electricity Balancing in Western Balkan Six region

Technical Assistance to the Implementation of Cross-border Electricity Balancing in Western Balkan Six region

client: Energy Community Secretariat (Austria)

type: Study and Software

finishing date: November 2018 (June 2019)

team: Zoran Vujasinovic – Project leader, D. Vlaisavljevic, D. Orlic, N. Jovic, O. Vukovic

Transmission, Policies

Montenegro
Defence Plan of the EPS of Montenegro - updated

Defence Plan of the EPS of Montenegro - updated

client: CGES AD (Montenegro)

type: Other

finishing date: September 2018 (December 2018)

team: Nebojsa Jovic – Task Leader, M. Vukovic- Consultant, M. Stojanovic, B. Sijakovic

Software

Serbia
Upgrade of TNA System

Upgrade of TNA System

client: Elektromreza Srbije AD (Serbia)

type: Software

finishing date: June 2018

team: EKC - Schneider Electric DMS; EKC team: Zoran Vujasinovic – Project Manager, D. Todorovic

Generation, Transmission

Montenegro

Electricity Network Expansion for the Development of RES; Feasibility Study and Preliminary Design

client: Mott MacDonald (United Kingdom)

type: Feasibility Study

finishing date: May 2016 (September 2018)

team: Slobodan Markovic - Network System Analyst (senior), Zoran Vujasinovic - Network System Analyst (senior)

Transmission, Market, Policies

Slovenia
Consulting services: Continental European Cost-Sharing Methodologies for Redispatching and Bidding Zone Review Study

Consulting services: Continental European Cost-Sharing Methodologies for Redispatching and Bidding Zone Review Study

client: ELES (Slovenia)

type: Study

finishing date: June 2018 (February 2019)

team: Zoran Vujasinovic - Project Manager, D. Vlaisavljevic, D. Todorovic, M. Ivanovic, I. Mihajlovic-Vlaisavljevic

Generation, Transmission

Serbia
Grid Connection Study for CHP (192 MW) to the Transmission Network of Serbia

Grid Connection Study for CHP (192 MW) to the Transmission Network of Serbia – TE-TO Pancevo

client: Elektromreza Srbije AD (Serbia)

type: Study

finishing date: August 2016 (August 2018)

team: Milan Ivanovic - Project Manager; M. Stojanovic, M. Vukovic - Consultant