Technical solution of connecting HPP Mrsovo to the EPS of Bosnia & Herzegovina
client: COMSAR ENERGY HYDRO d.o.o. (Bosnia and Herzegovina)
type: Study Case (Generation, Transmission, Renewable)
finishing date: February 2015
team: Maja Markovic - Project Manager, S. Markovic and M. Vukovic – Consultants, A. Oros, M. Stojkovic, Dj. Dobrijevic
Subject of the Study is to determine the place of point of common coupling of new HPP Mrsovo to electric power system of B&H in terms of lowest realization costs, and to propose the range of electromechanical parameters of hydro-units as well of corresponding step-up transformers, which will provide secure placement of power and energy produced in this HPP.
Type of services provided:
- Analysis of investment costs of connection realization
- Load flow analyses,
- Voltage profile analyses,
- Power losses analyses,
- Short circuit analyses,
- Transient stability analyses