References

Generation, Transmission

Ukraine
Ukraine Power System Support Project (UPSS): Steady State Analysis of 2015/2016 Winter Peak Regimes and Training (Phase IV)

The Ukraine Power System Support (UPSS) Project (Phase I - V)

client: USEA, USAID

type: Study (Transmission, Generation)

finishing date: November 2015

team: Milos Stojkovic – Project Manager, M. Ivanovic, M. Stojanovic

Generation, Transmission, Renewable, Power Quality

Serbia
Connection Study of Wind Power Plant Kovačica to the Transmission Network of Serbia

Connection Study of Wind Power Plant Kovačica to the Transmission Network of Serbia

client: Elektromreza Srbije - EMS (Serbia)

type: Study (Generation, Transmission, Power Quality, Renewable)

finishing date: July 2015

team: Milan Ivanovic - Project Leader, M. Vukovic and N. Jovic - Consultants, M. Stojanovic

Generation, Transmission

United Arab Emirates
Small Signal Stability Study for Barakah Nuclear Power Plant (BNPP  4x1500 MW)

Small Signal Stability Study for Barakah Nuclear Power Plant (BNPP 4x1500 MW)

client: KEPCO, TRANSCO, ENEC (UAE), Mott MacDonald (UAE)

type: Study (Transmission,  Generation)

finishing date: July 2015 (November 2015)

team: Mott MacDonald (UAE) - EKC (as subcontractor); EKC team: Predrag Miksa – Team Leader, N. Jovic – System Analyst, M. Stojanovic – System Analyst

Transmission, Market

SEE Electricity Market Perspectives until 2030: Assessing the Impact of Regional Connections to Italy

SEE Electricity Market Perspectives until 2030: Assessing the Impact of Regional Connections to Italy

client: USEA, USAID

type: Study (Market, Transmission)

finishing date: June 2015

team: Djordje Dobrijevic - Project Manager, D. Vlaisavljevic, N.Jovic - Consultant

Transmission, Market

The Kingdom of Saudi Arabia
Voltage Control and Reactive Power Planning - Study for SEC Southern Operating Area for 2019

Voltage Control and Reactive Power Planning - Study for SEC Southern Operating Area for 2019 System Plan

client: CESI (Italy), SEC (KSA)

type: Prefeasibility study (Market, Transmission)

finishing date: July 2015

team: Consortium CESI (Italy) - EKC; EKC team: Predrag Miksa – Task Leader, I. Mihajlovic – Transmission system expert

Generation, Transmission, Market

Serbia
The Analysis of EPS Position at the Regional Electricity Market of South-East Europe until 2030

The Analysis of EPS Position at the Regional Electricity Market of South-East Europe until 2030

client: Elektroprivreda Srbije EPS (Serbia)

type: Project  (Transmission, Generation, Market)

finishing date: July 2014 (July 2015)

team: Dragana Orlic - Project Leader, Z. Vujasinovic, N. Jovic, D. Vlaisavlјevic, I. Mihajlovic, M. Vukovic - Consultant

Generation, Transmission, Renewable, Power Quality

Serbia
Connection Study of Wind Power Plant Čibuk 1 to the Transmission Network of Serbia

Connection Study of Wind Power Plant Čibuk 1 to the Transmission Network of Serbia

client: Elektromreza Srbije - EMS (Serbia)

type: Study (Generation, Transmission, Power Quality, Renewable)

finishing date: May 2015

team: Nebojsa Jovic - Project Leader, M. Vukovic - Consultant, Milan Ivanovic

Generation, Renewable, Power Quality, Policies

Bosnia and Herzegovina
Compliance Testing Protocol

Compliance Testing Protocol

client: NOS BiH (Bosnia and Herzegovina)

type: Consultant services (Policies, Generation, Renewable, Power Quality)

finishing date: March 2015

team: Milan Ivanovic - Project Leader, M. Vukovic - Consultant, N. Jovic

Generation, Transmission

Bosnia and Herzegovina
Connection Study of TPP Banović (350MW) to Transmission Network

Connection Study of TPP Banović (350MW) to Transmission Network

client: RMU Banovici (Bosnia and Herzegovina)

type: Study (Transmission, Generation)

finishing date: June 2015

team: Consortium EI Hrvoje Pozar (Croatia) - EKC; EKC team: Slobodan Markovic - Project Manager, Dj. Dobrijevic - Dynamic Expert

Software

Upgrade of TNA software: TNA EMS 2.2

Upgrade of TNA software: TNA EMS 2.2

client: Elektromreza Srbije - EMS (Serbia)

type: Software License (Software)

finishing date: March 2015

team: Zoran Vujasinovic – Project Leader, B. Sijakovic, M. Markovic