References

Generation, Transmission

Ukraine
Ukraine Power System Support Project (UPSSP)

Ukraine Power System Support Project (UPSSP): Winter 2014/2015 Ukraine Power System Dynamic Analysis (Phase II)

client: USEA, USAID

type: Study (Transmission, Generation)

finishing date: February 2015

team: Milos Stojkovic – Project Manager, A. Oros

Generation, Transmission

Ukraine
Ukraine Power System Support Project (UPSS)

Ukraine Power System Support Project (UPSS): Winter 2014/2015 Ukraine Power System Analysis (Phase I)

client: USEA, USAID

type: Study (Transmission, Generation)

finishing date: March 2015

team: Milos Stojkovic – Project Manager, A. Oros, М. Markovic, S. Markovic

Transmission, Power Quality

Montenegro
Study of Power Supply for Construction Site of Motorway Section "Smokovac - Matesevo"

Study of Power Supply for Construction Site of Motorway Section "Smokovac - Matesevo"

client: CGES AD (Montenegro)

type: Study (Transmission, Power Quality)

finishing date: February 2015

team: Milan Ivanovic - Project Leader, M. Vukovic - Consultant

Generation, Transmission, Renewable

Bosnia and Herzegovina
Technical solution of connecting HPP Mrsovo to the EPS of Bosnia & Herzegovina

Technical solution of connecting HPP Mrsovo to the EPS of Bosnia & Herzegovina

client: COMSAR ENERGY HYDRO d.o.o. (Bosnia and Herzegovina)

type: Study Case (Generation, Transmission, Renewable)

finishing date: February 2015

team: Maja Markovic - Project Manager, S. Markovic and M. Vukovic – Consultants, A. Oros, M. Stojkovic, Dj. Dobrijevic

Generation, Transmission, Market

Serbia, Montenegro, Bosnia and Herzegovina
400 kV Interconnection Serbia – Montenegro – BiH

400 kV Interconnection Serbia – Montenegro – BiH; Feasibility & ESIA Assessment Study

client: WYG International Ltd. (United Kingdom) (Phase I and IIa), COWI A/S –on behalf of the COWI-IPF Consortium 2 (Denmark) (Phase IIb)

type: Feasibility Study  (Transmission, Generation, Market)

finishing date: October 2014 (Phase I and IIa), February 2015 (Phase IIb)

team: Snezana Mijailovic - Project Manager, Slobodan Markovic - Transmission Planning engineer, P. Miksa - Network System Analyst (senior), T. Martinovic - Network System Analyst (junior), D. Orlic – Market System Analyst (senior)

Generation, Transmission

Bosnia and Herzegovina
Connection Study of TPP Stanari to Transmission Network

Connection Study of TPP Stanari to Transmission Network

client: EFT Rudnik and TE Stanari (B&H)

type: Feasibility Study (Transmission, Generation)

finishing date: November 2014

team: Slobodan Markovic – Project Manager, M. Vukovic and Dj. Dobrijevic – Consultants, M. Ivanovic, A. Oros, M. Markovic, B. Sijakovic, N. Jovic - Reviewer

Market, Software

Southeast Europe
Project Extension MC Simulator

Bidding Curves for Market Coupling Simulation in SEE (Project Extension MC Simulator)

client: SEE TSOs, Energy Community Secretariat (Austria)

type: Study (Market, Software)

finishing date: September 2014

team: Zoran Vujasinovic – Project Leader, D. Vlaisavljevic, I. Mihajlovic, M. Vukovic – Consultant

Market

Southeast Europe
lmpact Assessment of Regional Balancing Integration in SEE

lmpact Assessment of Regional Balancing Integration in the Southeast European Electricity Market

client: Energy Community Secretariat (Austria)

type: Study (Market)

finishing date: September 2014 (December 2014)

team: Zoran Vujasinovic - Project Leader, M. Vukovic - Consultant, N. Jovic, D. Vlaisavljevic

Transmission, Market

Black Sea Region
Study Black Sea CBA Phase I

Black Sea Regional Transmission System Planning Project (BSTP) - Techno-Economic Evaluation of Candidate Transmission Projects (Phase I)

client: USEA, USAID

type: Study (Transmission, Market)

finishing date: September 2014

team: Milos Stojkovic – Project Manager, S. Mijailovic – Consultant and Coordinator, М. Markovic, B. Sijakovic

Generation, Transmission, Market

Armenia
Energy Assistance Program for Armenia

Energy Assistance Program for Armenia

client: USEA, USAID

type: Study  (Transmission, Generation, Market)

finishing date: September 2014 (December 2014)

team: Zoran Vujasinovic – Project Leader, N. Jovic, P. Miksa, D. Vlaisavljevic

Pages