Generation, Transmission

Montenegro
Study HPP Komarnica CGES

Prefeasibility Study of Connection of HPP Komarnica to the transmission network of Montenegro

client: CGES (Montenegro)

type: Prefeasibility study (Transmission, Generation)

finishing date: July 2013

team: Tomo Martinovic – Project Leader, M. Vukovic – Consultant, B. Sijakovic

Transmission, Software

Bosnia and Herzegovina
Study TNA NOS B&H

TNA NOS BiH - Software for load flow in accordance with ENTSO-E standards and requirements

client: Independent System Operator B&H (B&H)

type: Software License (Software, Transmission)

finishing date: June 2013

team: Zoran Vujasinovic - Project Leader, N. Jovic

Transmission, Market

South Caucasus
Study South Caucasus Phase II

Stock Taking: Regional Power Trade in Southern Caucasus - Phase II

client: World Bank

type: Study (Transmission, Market)

finishing date: September 2013

team: Zoran Vujasinovic - Project Leader, S. Mijailovic, M. Stojkovic, P. Miksa - Consultant

Market, Renewable, Policies

Bosnia and Herzegovina
Analysis of technical, market and regulatory aspects and the position of »Hidroelektrane na Trebišnjici« regarding the construction of TS Plat

Analysis of technical, market and regulatory aspects and the position of »Hidroelektrane na Trebišnjici« regarding the construction of TS Plat

client:   HE na Trebisnjici (Bosnia and Herzegovina)

type:   Study (Market, Renewable, Policies)

finishing date:   May 2013

team:   Zoran Vujasinovic – Project Leader, M. Vukovic – Consultant, T. Martinovic

Power Quality

Montenegro
Study PQ Zeljezara CGES

Impact of Electric Arc Furnance in “Zeljezara” Niksic to Power Quality in Transmission System

client: CGES (Montenegro)

type: Study (Power Quality)

finishing date: May 2013

team: Andrija Oros – Project Leader, T. Martinovic

Power Quality

Oman
Study OMAN compensation

Reactive Power Compensation Requirements for OETC with 400KV System in 2016

client: OETC (Oman), EDF Cist (France)

type: Pre-Feasibility study  (Power Quality)

finishing date: May 2013 (December 2013)

team: EDF Cist (France) - EKC consortium; EKC team: Predrag Miksa – Task Leader, Milos Stojkovic – Transmission system expert

Market, Policies

Montenegro
Market valorization of the HVDC cable

Market valorization of the HVDC cable Montenegro-Italy from the position of the Montenegrin TSO CGES

client: CGES (Montenegro)

type: Study (Market, Policies)

finishing date: February 2013

team: Zoran Vujasinovic – Project Leader, D. Orlic, S. Markovic, T. Martinovic, D. Vlaisavljevic, M. Vukovic - Consultant

Transmission, Market

Slovenia
Study Benefit Analysis ELES

New 400 kV Interconnection of Slovenia – Benefit Analysis

client: ELES (Slovenia)

type: Study  (Transmission, Market)

finishing date: February 2013

team: Zoran Vujasinovic – Project Leader, D. Orlic, S. Markovic, T. Martinovic, D. Vlaisavljevic, M. Vukovic - Consultant

Generation, Transmission, Renewable

FRY of Macedonia
Dynamic stability and power quality analyses for connection study of Wind Power Plant Bogdanci (36.8 MW)

Dynamic stability and power quality analyses for connection study of Wind Power Plant Bogdanci (36.8 MW) to the transmission network of Macedonia

client: MEPSO (Macedonia)

type: Study (Renewable, Transmission, Generation)

finishing date: February 2013

team: Nebojsa Jovic - Project leader, M. Vukovic - Consultant, M. Stojkovic, A. Oros

Transmission, Market

Southeast Europe
Electric Power System Evolution with Market and Network Analysis

SEE Electric Power System Evolution with Market and Network Analysis 2011-2016

client: Terna Crna Gora (Montenegro)

type: Study (Transmission, Market)

finishing date: December 2012 (March 2014)

team: Tomo Martinovic – Project Leader, Dj. Dobrijevic, D. Orlic, M. Stojkovic, S. Markovic, A. Oros, Z. Vujasinovic – Consultant